Dominion Energy And Duke Energy Cancel The Atlantic Coast Pipeline

Dominion Energy and Duke Energy today announced the cancellation of the Atlantic Coast Pipeline (ACP) due to ongoing delays and increasing cost uncertainty which threaten the economic viability of the project.

Despite last month’s overwhelming 7-2 victory at the United States Supreme Court, which vindicated the project and decisions made by permitting agencies, recent developments have created an unacceptable layer of uncertainty and anticipated delays for ACP.

A series of legal challenges to the project’s federal and state permits caused significant project cost increases and timing delays. As a result, recent public guidance of project cost has increased to $8 billion from the original estimate of $4.5 to $5.0 billion. In addition, the most recent public estimate of commercial in-service in early 2022 represents a nearly three-and- a-half-year delay with uncertainty remaining.

Thomas F. Farrell, II, Dominion Energy chairman, president, and chief executive officer, and Lynn J. Good, Duke Energy chair, president, and chief executive officer, said:

“We regret that we will be unable to complete the Atlantic Coast Pipeline. For almost six years we have worked diligently and invested billions of dollars to complete the project and deliver the much-needed infrastructure to our customers and communities. Throughout we have engaged extensively with and incorporated feedback from local communities, labor and industrial leaders, government and permitting agencies, environmental interests and social justice organizations. We express sincere appreciation for the tireless efforts and important contributions made by all who were involved in this essential project. This announcement reflects the increasing legal uncertainty that overhangs large-scale energy and industrial infrastructure development in the United States. Until these issues are resolved, the ability to satisfy the country’s energy needs will be significantly challenged.”

The Atlantic Coast Pipeline was initially announced in 2014 in response to a lack of energy supply and delivery diversification for millions of families, businesses, schools, and national defense installations across North Carolina and Virginia.

This afternoon NC Governor Roy Cooper issued a statement saying, “This decision and the changing energy landscape should lead to cleaner and more reliable energy generation in North Carolina. Our Clean Energy Plan provides an excellent framework and stakeholder process for renewable energy moving forward.”


Related Stories

Johnston County Residents Unite To Fight Atlantic Coast Pipeline

Johnston County Gives Easement To Atlantic Coast Pipeline

Commissioners Hear Concerns About Atlantic Coast Pipeline

Council Approves Pipeline Contractor Yard

Economic Development Advisory Board Makes 7 Recommendations To Commissioners